Phase I..........................................August
1-January 10, 2006 Develop Operational Program Phase
II..........................................January 10-March 31, 2006
Review/Accept Operational Program Develop Operational Staffing/Costs
Public Outreach Phase III..........................................April
1-May 30, 2006 Develop Functional Space/Equipment Program
Public Outreach Contract for Public Outreach Planning Phase
IV..........................................June 1-July 31, 2006
Finalize Operational Program (Bed and Staffing Plan) Finalize Space
Program Finalize Capital Cost Projections Reactivate Environmental
Impact Statement (EIS) process Public Outreach Phase V..........................................August
1-November 30, 2006 Finalize Operating Cost Projections
Develop Schematic Design Update Policy Makers and Public Phase
VI.............................December 1, 2006-September 30, 2007
Complete/Distribute Draft EIS Begin CUP Application Process with Tumwater
CUP Finalized (9/25/07)
Issue Final Environmental Impact Statement (FEIS)
Design Development
Secure Budget/Design Approvals
Develop Construction Drawings
Begin Project Permitting Process with City of Tumwater
Begin
Development of Bid Documents
Begin Implementation of Risk Assessment
Tool
Phase VII..........................................October 1 - July 17, 2008
Finalize Early Site Bid Documents
Bid Early Site Package Project/Select Contractor
Complete Early Site Work
Phase
VIII..............................July 2008 - December 31, 2010
Finalize Bid Documents
Bid Project/Select Contractor
Construction
Construction Close-out
Revised 4/17/2009 |