ARC Construction Progressing

Aerial February 2010

Aerial View - February 2010

View Aerial Photos

View Site Plans


Consolidated Jail Recommendation

View report and recommendations with all attachments from the ARC Operating Costs Task Force. (PDF 3MB)

Accountability and Restitution Center Planning Process

Phase I..........................................August 1-January 10, 2006
• Develop Operational Program

Phase II..........................................January 10-March 31, 2006
• Review/Accept Operational Program
• Develop Operational Staffing/Costs
• Public Outreach

Phase III..........................................April 1-May 30, 2006
• Develop Functional Space/Equipment Program
• Public Outreach
• Contract for Public Outreach Planning

Phase IV..........................................June 1-July 31, 2006
• Finalize Operational Program (Bed and Staffing Plan)
• Finalize Space Program
• Finalize Capital Cost Projections
• Reactivate Environmental Impact Statement (EIS) process
• Public Outreach

Phase V..........................................August 1-November 30, 2006
• Finalize Operating Cost Projections
• Develop Schematic Design
• Update Policy Makers and Public

Phase VI.............................December 1, 2006-September 30, 2007
• Complete/Distribute Draft EIS
• Begin CUP Application Process with Tumwater
CUP Finalized (9/25/07)
• Issue Final Environmental Impact Statement (FEIS)
• Design Development
• Secure Budget/Design Approvals
• Develop Construction Drawings
• Begin Project Permitting Process with City of Tumwater
• Begin Development of Bid Documents
• Begin Implementation of Risk Assessment Tool

Phase VII..........................................October 1 - July 17, 2008
• Finalize Early Site Bid Documents
• Bid Early Site Package Project/Select Contractor
• Complete Early Site Work

Phase VIII..............................July 2008 - December 31, 2010
• Finalize Bid Documents
• Bid Project/Select Contractor
• Construction
• Construction Close-out

 

Revised 4/17/2009

What is an ARC?
Past Efforts
What Is the Recommendation?
Location
Frequently Asked Questions [PDF]
Consolidated Jail FAQ [PDF]
Facility - Programs Offered
Schedule
Environmental Review Process