Accountability and Restitution Center Planning Process

Phase I..........................................August 1-January 10, 2006
• Develop Operational Program

Phase II..........................................January 10-March 31, 2006
• Review/Accept Operational Program
• Develop Operational Staffing/Costs
• Public Outreach

Phase III..........................................April 1-May 30, 2006
• Develop Functional Space/Equipment Program
• Public Outreach
• Contract for Public Outreach Planning

Phase IV..........................................June 1-July 31, 2006
• Finalize Operational Program (Bed and Staffing Plan)
• Finalize Space Program
• Finalize Capital Cost Projections
• Reactivate Environmental Impact Statement (EIS) process
• Public Outreach

Phase V..........................................August 1-November 30, 2006
• Finalize Operating Cost Projections
• Develop Schematic Design
• Update Policy Makers and Public

Phase VI.............................December 1, 2006-September 30, 2007
• Complete/Distribute Draft EIS
• Begin CUP Application Process with Tumwater
CUP Finalized (9/25/07)
• Issue Final Environmental Impact Statement (FEIS)
• Design Development
• Secure Budget/Design Approvals
• Develop Construction Drawings
• Begin Project Permitting Process with City of Tumwater
• Begin Development of Bid Documents
• Begin Implementation of Risk Assessment Tool

Phase VII..........................................October 1 - July 17, 2008
• Finalize Early Site Bid Documents
• Bid Early Site Package Project/Select Contractor
• Complete Early Site Work

Phase VIII..............................July 2008 - December 31, 2010
• Finalize Bid Documents
• Bid Project/Select Contractor
• Construction
• Construction Close-out

 

Revised 4/17/2009


What is an ARC?
Past Efforts
What Is the Recommendation?
Location
Frequently Asked Questions [PDF]
Consolidated Jail FAQ [PDF]
Facility - Programs Offered
Schedule
Environmental Review Process